Posted to Dan Jones Widening on August 14, 2025 at 1:29 PM by Angel Gino-Gino
All work on the Dan Jones Phase 2 is now completed.
Posted to Dan Jones Widening on August 14, 2024 at 1:23 PM by Angel Gino-Gino

Construction is on track. The curbs and first layer of asphalt are done on Dan Jones north of 150; the bridge backfill is done. Storm drains are near completion on County Road 150 South. The contractors are stabilizing soil and starting the Dan Jones South of 150 storm drainage. They are continually installing structures and pipes throughout this section of Dan Jones.
Dan Jones Road will remain closed from County Road 150 South, also called Oriole Point Drive, to County Road 100 South.
If you have any questions, please email Public Works Director Steve Moore.
Tag(s): Dan Jones Widening Phase 2
Posted to Dan Jones Widening on March 28, 2024 at 2:48 PM by Jared Wade

Construction is scheduled to begin on April 1st on Dan Jones Road from County Road 150 South to County Road 100 South. The Contractor will start installing the new stormwater sewer along the east side of Dan Jones Road. This work is outside of the current roadway, but minor traffic slowdowns may occur from April 1st through May 28th, with the possibility of earlier or later closures if needed.
Dan Jones Road from County Road 150 South, also called Oriole Point Drive, to County Road 100 South is scheduled to be closed to all traffic on May 28th.
If you have any questions, please email Public Works Director Steve Moore.