Posted on January 18, 2024 at 9:26 AM by Jared Wade
Current Status – All lanes open to traffic. Northbound right lane will remain a merged lane until the Hendricks County Bridge is constructed to a four lane bridge possibly in 2025. The bridge project is completely overseen by Hendricks County.
Remaining Work- In April 2024, the surface layer of asphalt will be installed, then the final pavement markings will also be installed, completing the project, hopefully, by the end of May 2024.