Dan Jones Widening - Phase 3 September 5th, 2025 Update

Posted on September 5, 2025 at 10:58 AM by Angel Gino-Gino

Howard Companies will be performing asphalt patching work on Dan Jones Road for the gas line south of the County Side crossing. Howard’s crews will be onsite Tuesday and Wednesday, September 9–10, 2025.

To reduce disruptions, they will be repairing the trench  ½ at a time. There may be minimal traffic stoppages.

Traffic Impact: Traffic control materials will be on-site to safely direct traffic around the work zones as crews work on each side of the road. Please plan accordingly and drive with caution in the area.

  1. Avon_Full Color_Symbol Only

Contact Us

  1. 6570 East US Highway 36
    Avon, IN 46123
    Phone: 317-272-0948


    Note: The office will be closed for lunch every day
    11:30 am to 12:30 pm

Hours

  1. Monday: 8 am to 4:30 pm
    Tuesday: 8 am to 4:30 pm
    Wednesday: 8 am to 4:30 pm
    Thursday: 8 am to 4:30 pm
    Friday: 8 am to 4:30 pm
    Saturday & Sunday: Closed

Government Websites by CivicPlus®
Arrow Left Arrow Right
Slideshow Left Arrow Slideshow Right Arrow